====== Why Don't We Use Gantt Charts in Agile? ====== | ====== Why Don't We Use Gantt Charts in Agile? ====== | ||
- | |||
- | ====== Premise ====== | ||
Most of the time when we go down the path of an agile implementation Gantt charts do not help much. I've seen them used to describe high level plan, almost like a roadmap more as a result of a need to meet a governance standard but not really useful as a tool for managing a project (or dependencies). | Most of the time when we go down the path of an agile implementation Gantt charts do not help much. I've seen them used to describe high level plan, almost like a roadmap more as a result of a need to meet a governance standard but not really useful as a tool for managing a project (or dependencies). | ||
Line 9: | Line 7: | ||
====== Discussion ====== | ====== Discussion ====== | ||
- | The reason | + | The reason |
In particular, tasks are managed by the team. Dependencies therefore become a lot more localized and dealt with through discussion with the team - we get the next piece of value as a result of having teams task the work required that deliver that value. If they need some task completed first that becomes part of the discussion. Sometimes that discussion will bleed into a prioritization discussion (eg team says "if you want this higher priority value item first, we might be better off doing this lower value item first" or one team talks to another about the relative prioritization' | In particular, tasks are managed by the team. Dependencies therefore become a lot more localized and dealt with through discussion with the team - we get the next piece of value as a result of having teams task the work required that deliver that value. If they need some task completed first that becomes part of the discussion. Sometimes that discussion will bleed into a prioritization discussion (eg team says "if you want this higher priority value item first, we might be better off doing this lower value item first" or one team talks to another about the relative prioritization' | ||
Line 16: | Line 14: | ||
For additional discussion on Gantt charts at [[http:// | For additional discussion on Gantt charts at [[http:// | ||
- | Also see [[blog: | + | Also see [[what_is_the_best_approach_to_making_decisions_in_our_context|Why Doesn' |